10437 Berlin

Construction time: July 2018
Problem solution: High temperature resistance and tightness against concrete pressure during foundation construction.
A 5-fold silage slab for a driving silo was created. According to the lower water authority, the pipelines had to be completely welded to ensure the highest possible safety against leaking seepage.
Volume:
350 m DN 110 PP sewer pipe according to DIN EN 14758 incl. Molded parts