47669 Wachtendonk
Construction time: September 2017
Design, construction for drainage – new construction of a driving silo plant
Project Scope:
1 JGS tank 45 m³ DN 2200, 13.00 m
120 pieces IP-plus welding rings DN 250, DN 200 and DN 150
8 separation shafts DN 400/160